NEM Gas Baseload Stats

CCGT and steam-cycle gas thermal plant across the NEM — baseload and mid-merit units, not open-cycle peakers. Stats for the selected period. Data through 13 Jun 2026, 13:30 AEST.

Browse by type
Energy revenue (× MLF)
$59.4k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
1,695.4 MWh
Capacity factor
4.1%
Generators
12

Energy revenue = cleared MW × (5/60 h) × regional RRP × MLF. FCAS revenue = sum of cleared FCAS MW × (5/60 h) × regional FCAS price × MLF (raise/lower 6s, 60s, 5min, reg). FCAS volume = total FCAS enablement MWh across all services. Capacity factor = dispatched MWh ÷ (nameplate MW × period hours). SRMC from financial assumptions. Not AEMO settlement data.

Site DUID Region Tech Energy rev. (× MLF) FCAS rev. (× MLF) FCAS MWh MWh dispatch MWh available Capacity factor Est. SRMC
Yarwun 1 YARWUN_1 QLD1 Turbine - CCGT $35.2k $0 925.2 673.7 38.1% $84.30 View
Tallawarra TALWA1 NSW1 Turbine - CCGT $24.8k $0 415.5 937.5 7.7% $84.30 View
Osborne OSB-AG SA1 Turbine - CCGT $674 $0 110.2 4.5% $84.30 View
Newport NPS VIC1 Turbine - Steam Sub Critical $0 $0 0.0% $2.00 View
Pelican Point PPCCGT SA1 Turbine - CCGT $0 $0 0.0% $84.30 View
Torrens Island B TORRB1 SA1 Turbine - Steam Sub Critical $0 $0 0.0% $2.00 View
Torrens Island B TORRB3 SA1 Turbine - Steam Sub Critical $0 $0 0.0% $2.00 View
Torrens Island B TORRB4 SA1 Turbine - Steam Sub Critical $0 $0 0.0% $2.00 View
Tamar Valley Combined Cycle TVCC201 TAS1 Turbine - CCGT $0 $0 0.0% $84.30 View
Townsville Power Station YABULU QLD1 Turbine - CCGT $0 $0 0.0% $84.30 View
Townsville Power Station YABULU2 QLD1 Turbine - CCGT $0 $0 0.0% $84.30 View
Torrens Island B TORRB2 SA1 Turbine - Steam Sub Critical $-1.2k $0 244.6 816.7 9.1% $5.47 View