Warwick Solar Farm (WARWSF2)

Solar · The University of Queensland · Solar PV - Single axis tracking

Operational AEMO: In Service QLD1 Solar - Solar NEM data · 30 days
32 MW
Registered nameplate capacity
30 days revenue
$93.1k
Capacity factor
8.8%
Revenue / MWh
$45.97
Est. SRMC
$0.25/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
32 MW

AEMO status In Service
Project status Operational (AI)

AEMO registration shows Warwick Solar Farm (WARWSF2) in service with commissioning completed 2023-04-01; project is therefore operational.

Region QLD1
Coordinates

MLF 0.9888
DUID WARWSF2
Owner The University of Queensland
Commissioned Apr 2023
Expected closure 2045
Closure date
Technology Solar PV - Single axis tracking
Fuel Solar - Solar
Module OEM Jinko Solar
Module / inverter supplier PV modules / inverter supplier
Inverter OEM Sungrow
Inverter model SG250HX
Equipment confidence low
Stats window
14 May 2026 18:15 → 13 Jun 2026 18:15 AEST

Dispatch & revenue

14 May 2026 18:15 → 13 Jun 2026 18:15 AEST

Energy revenue (× MLF)
$93.1k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
2,024.7 MWh
Available
2,522.0 MWh
Curtailed
525.1 MWh
Curtailment
20.8%
of available
MLF used
0.9888
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9847
2025-07-01 0.9888

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (tracking)
Capacity
32 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.25/MWh
Capex total (greenfield) default
$41.73M

Shown in table
$41.73M (2026 real AUD)

Capex refurbishment
Capex / MW default
$1,300,000

Shown in table
$1.30M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$20,000

Shown in table
$20.0k (2026 real AUD)

Variable OPEX / MWh default
$0.25

Shown in table
$0.25 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: unknown · Status: needs review · Capex basis: unknown