Solar · Quorn Park Solar Farm Pty Ltd as the trustee for Quorn Park Solar Farm Trust · Solar PV - Single axis tracking
Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.
19 Sep 2026 04:35 → 20 Sep 2026 04:35 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.INITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.| Effective from | MLF |
|---|---|
| 2026-01-20 | 1.0190 |
| 2026-02-03 | 0.9176 |
| 2026-07-01 | 0.9032 |
| Capex total (greenfield) |
$200.42M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$2,070,475
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX (annual) |
$2.04M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$21,097
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$0.26
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Reported project investment value over $190 million for the Quorn Park Hybrid Project (98 MWdc solar farm + 20 MW/40 MWh BESS). Registered DUID capacity is 96.8 MW; capex per MW is calculated using this capacity. No separate plant-specific O&M or asset life source found in the search results, so internal defaults were used for O&M and emissions. Project appears to have been developed by Enel Green Power Australia / Potentia Energy and INPEX. The reported investment figure is for the full hybrid project, not a refurbishment.