Moranbah North (MBAHNTH)

Coal · EDL Projects Australia Pty Ltd · Reciprocating Engine - Spark ignition

Operational AEMO: In Service QLD1 Fossil - Waste Coal Mine Gas NEM data · 1h
64 MW
Registered nameplate capacity
1h revenue
$362
Capacity factor
7.2%
Revenue / MWh
$79.03
Est. SRMC
$57.00/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
64 MW

AEMO status In Service
Project status Operational (AI)

EDL project page and fact sheet describe Moranbah North as owned/operated and producing electricity; AEMO lists it In Service.

Region QLD1
Coordinates -22.00163, 148.04661 (AI)

dateandtime.info gives Moranbah town coordinates; no site-specific public coordinates found for the power station.

MLF 1.0081
DUID MBAHNTH
Owner EDL Projects Australia Pty Ltd
Commissioned
Expected closure 2038
Closure date
Technology Reciprocating Engine - Spark ignition
Fuel Fossil - Waste Coal Mine Gas
Plant supplier EDL
Boiler / turbine equipment 3 MW reciprocating engine blocks (x21)
Equipment confidence high
Stats window
14 Jun 2026 00:00 → 14 Jun 2026 00:30 AEST

Dispatch & revenue

14 Jun 2026 00:00 → 14 Jun 2026 00:30 AEST

Energy revenue (× MLF)
$362
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
4.6 MWh
Available
MWh
Curtailed
MWh
Curtailment
of available
MLF used
1.0081
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9981
2025-07-01 1.0081

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Waste / landfill gas
Capacity
64 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$57.00/MWh
Capex total (greenfield) default
$159.60M

Shown in table
$159.60M (2026 real AUD)

Capex refurbishment
Capex / MW default
$2,500,000

Shown in table
$2.50M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$50,000

Shown in table
$50.0k (2026 real AUD)

Variable OPEX / MWh default
$3.00

Shown in table
$3.00 (2026 real AUD)

Fuel cost / GJ default
$6.00

Shown in table
$6.00 (2026 real AUD)

Heat rate GJ/MWh default
9.00

Shown in table
$9.00 (2026 real AUD)

Confidence: unknown · Status: needs review · Capex basis: unknown