Kogan Creek (KPP_1)

Coal · Kogan Creek Power Station Pty Ltd · Turbine - Steam Super Critical

Operational AEMO: In Service QLD1 Fossil - Black Coal NEM data · 24 hours
744 MW
Registered nameplate capacity
24 hours revenue
$470.4k
Capacity factor
49.3%
Revenue / MWh
$53.39
Est. SRMC
$52.60/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
744 MW

AEMO status In Service
Project status Operational (AI)

CS Energy Kogan Creek Power Station page (csenergy.com.au) describes the plant as a 750 MW single-unit power station in service/operating near Chinchilla.

Region QLD1
Coordinates -26.91640, 150.74917 (AI)

Global Energy Observatory lists Kogan Creek Coal Power Plant at latitude -26.9164, longitude 150.74917.

MLF 0.9737
DUID KPP_1
Owner Kogan Creek Power Station Pty Ltd
Commissioned
Expected closure 2042
Closure date
Technology Turbine - Steam Super Critical
Fuel Fossil - Black Coal
Steam turbine OEM Siemens
Turbine / boiler supplier Varioplant 700
Equipment confidence high
Stats window
12 Jun 2026 18:30 → 13 Jun 2026 18:30 AEST

Dispatch & revenue

12 Jun 2026 18:30 → 13 Jun 2026 18:30 AEST

Energy revenue (× MLF)
$470.4k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
8,810.5 MWh
Available
7,546.5 MWh
Curtailed
540.7 MWh
Curtailment
7.2%
of available
MLF used
0.9737
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9692
2025-07-01 0.9737

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Black coal
Capacity
744 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$52.60/MWh
Capex total (greenfield)
$1,986.75M

Shown in table
$1,986.75M (2026 real AUD)

Reported / source value
$1,200.00M (2007 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Independent project-opening summary confirms the reported total project cost at opening.

Reference
Kogan Creek power station opening (Journal Article) (high confidence)
Source recorded 09 Jun 2026

Capex refurbishment
$40.89M

Shown in table
$40.89M (2026 real AUD)

Reported / source value
$35.00M (2022 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
This is a brownfield overhaul/refurbishment cost and is recorded separately from original capex.

Reference
Kogan Creek Power Station readies for $35 million overhaul (high confidence)
Source recorded 09 Jun 2026

Capex / MW derived
$2,670,370

Shown in table
$2.67M (2026 real AUD)

Reported / source value
$1.61M (2007 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

Variable OPEX / MWh default
$4.00

Shown in table
$4.00 (2026 real AUD)

Fuel cost / GJ default
$4.50

Shown in table
$4.50 (2026 real AUD)

Heat rate GJ/MWh default
10.80

Shown in table
$10.80 (2026 real AUD)

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 09 Jun 2026

Notes
Greenfield capex is based on CS Energy / project-opening sources describing the $1.2 billion plant opening in 2007. A separate brownfield overhaul cost of $35 million in 2022 is recorded as refurbishment only. No plant-specific O&M, fuel price, or heat-rate source was located in the searched official materials; those fields remain blank rather than inferred.