Hunter Power Station (HUNTER2)

Gas Peakers · Snowy Hydro Limited · Turbine - OCGT

Operational AEMO: Committed NSW1 Fossil - Natural Gas Pipeline NEM data · 7 days
375 MW
Registered nameplate capacity
7 days revenue
$0
Capacity factor
0.0%
Revenue / MWh
Est. SRMC
$152.46/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
375 MW

AEMO status Committed
Project status Operational (AI)

Snowy Hydro project page notes the site was commissioned and is in service; commissioning date given as 2025-07-01.

Region NSW1
Coordinates

MLF 0.9692
DUID HUNTER2
Owner Snowy Hydro Limited
Commissioned Sep 2025
Expected closure 2064
Closure date
Technology Turbine - OCGT
Fuel Fossil - Natural Gas Pipeline
Gas turbine OEM Mitsubishi Power
Turbine / engine model M701F
Equipment confidence high
Stats window
07 Jun 2026 02:20 → 14 Jun 2026 02:20 AEST

Dispatch & revenue

07 Jun 2026 02:20 → 14 Jun 2026 02:20 AEST

Energy revenue (× MLF)
$0
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
MWh
Available
MWh
Curtailed
MWh
Curtailment
of available
MLF used
0.9692
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2025-03-25 0.9767
2025-07-01 0.9692

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
OCGT
Capacity
375 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$152.46/MWh
Capex total (greenfield)
$589.27M

Shown in table
$589.27M (2026 real AUD)

Reported / source value
$539.77M (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Snowy Hydro reported the Hunter Power Project target cost at $950 million in its 2023 reset announcement.

Reference
Hunter Power Project Archives (high confidence)
Source recorded 04 Jun 2026

Capex refurbishment
Capex / MW derived
$1,571,391

Shown in table
$1.57M (2026 real AUD)

Reported / source value
$1.44M (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated per-MW capex using the reported project cost and the user-provided DUID capacity of 375 MW.

Reference
Hunter Power Project Archives (medium confidence)
Source recorded 04 Jun 2026

Fixed OPEX (annual)
$5.80M

Shown in table
$5.80M (2026 real AUD)

Reported / source value
$5.31M (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$15,469

Shown in table
$15.5k (2026 real AUD)

Reported / source value
$14.2k (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
AEMO/Aurecon large gas turbine fixed O&M was used as the closest published OCGT benchmark.

Reference
2024 Energy Technology Cost and Technical Parameter Review (high confidence)
Source recorded 04 Jun 2026

Variable OPEX / MWh
$15.05

Shown in table
$15.05 (2026 real AUD)

Reported / source value
$13.79 (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
AEMO/Aurecon published variable O&M for the large gas turbine case.

Reference
2024 Energy Technology Cost and Technical Parameter Review (high confidence)
Source recorded 04 Jun 2026

Fuel cost / GJ
$13.10

Shown in table
$13.10 (2026 real AUD)

Reported / source value
$12.00 (2023 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No authoritative plant-specific fuel price was identified in the searched sources, so the provided fallback was retained.

Heat rate GJ/MWh
10.49

Shown in table
$10.49 (2026 real AUD)

How this was derived
AEMO/Aurecon published the large gas turbine heat rate used as an OCGT proxy.

Reference
2024 Energy Technology Cost and Technical Parameter Review (high confidence)
Source recorded 04 Jun 2026

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 04 Jun 2026

Notes
Greenfield Hunter Power Project target cost was reported by Snowy Hydro as $950 million after the 2023 project reset. The site has 660 MW initially available to the grid, but the registered unit capacity is 375 MW for HUNTER2; per-MW capex is therefore calculated using the DUID capacity provided by the user. O&M and performance values are taken from AEMO/Aurecon 2024 technology-cost review for large OCGT-style gas turbines. Heat rate source is an AEMO/Aurecon table for large gas turbines; used as an OCGT proxy.

Sources