Wind · Gunning Wind Energy Developments · Wind Turbine - Onshore
Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.
13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.| Effective from | MLF |
|---|---|
| 2024-07-01 | 0.9317 |
| 2025-07-01 | 0.9521 |
| Capex total (greenfield) |
$226.85M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$4,878,534
Shown in table Reported / source value |
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr default |
$55,000
Shown in table How this was derived Reference |
| Variable OPEX / MWh default |
$0.50
Shown in table How this was derived Reference |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 08 Jun 2026
Notes
Project investment reported by ACCIONA as $147 million AUD during construction. Operational since May 2011. No project-specific O&M or refurbishment cost found; internal/default O&M values were not used because source-backed plant-specific operating data was not located. Asset life set to 25 years based on ACCIONA fact sheet / project materials.