Challicum Hills (CHALLHWF)

Wind · Pacific Hydro Challicum Hills Pty Ltd · Wind Turbine - Onshore

AEMO: removed VIC1 Wind - Wind NEM data · 24 hours
53 MW
Registered nameplate capacity
24 hours revenue
$-2.2k
Capacity factor
23.3%
Revenue / MWh
$-7.62
Est. SRMC
$0.53/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. VIC1 regional price (RRP) on right axis.

Key information
Capacity
53 MW

AEMO status removed
Project status (AI)

Region VIC1
Coordinates

MLF 0.9825
DUID CHALLHWF
Owner Pacific Hydro Challicum Hills Pty Ltd
Commissioned
Expected closure 2025
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM
Turbine model
Stats window
12 Jun 2026 00:00 → 12 Jun 2026 23:59 AEST

Dispatch & revenue

12 Jun 2026 00:00 → 12 Jun 2026 23:59 AEST

Energy revenue (× MLF)
$-2.2k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
293.7 MWh
Available
MWh
Curtailed
MWh
Curtailment
of available
MLF used
0.9825
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9718
2025-07-01 0.9825

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
53 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.53/MWh
Capex total (greenfield)
$143.94M

Shown in table
$143.94M (2026 real AUD)

Reported / source value
$76.00M (2002 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Official owner site reports the original project cost as A$76 million.

Reference
Challicum Hills wind farm | Pacific Blue (high confidence)
Source recorded 06 Jun 2026

Capex refurbishment
Capex / MW derived
$2,741,703

Shown in table
$2.74M (2026 real AUD)

Reported / source value
$1.45M (2002 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Per-MW capex derived from the reported total cost and registered capacity.

Reference
Challicum Hills wind farm | Pacific Blue (high confidence)
Source recorded 06 Jun 2026

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

How this was derived
Searches found the plant page and cost references, but no reliable owner/government source for fixed O&M at this site.

Variable OPEX / MWh
$0.53

Shown in table
$0.53 (2026 real AUD)

Reported / source value
$0.50 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No site-specific variable O&M source found; fallback preserved for wind_onshore.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Pacific Blue states Challicum Hills was completed in August 2003 and that construction commenced in October 2002. The reported A$76 million project cost is treated as greenfield original construction cost. No plant-specific fixed O&M figure was found, so the internal fallback was not used to populate fixed OPEX here because the instructions prefer search-backed values only.

Sources