Coal · Braemar Power Project Pty Ltd · Turbine - OCGT
Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.
15 May 2026 06:10 → 14 Jun 2026 06:10 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.| Effective from | MLF |
|---|---|
| 2024-07-01 | 0.9627 |
| 2025-07-01 | 0.9667 |
| Capex total (greenfield) |
$237.97M
Shown in table Reported / source value How this was derived |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$1,265,823
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$2.86M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$15,190
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$4.94
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ default |
$12.00
Shown in table |
| Heat rate GJ/MWh default |
10.50
Shown in table |
Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 05 Jun 2026
Notes
No reliable plant-specific greenfield capital cost announcement for Braemar Power Project Pty Ltd / BRAEMAR2 was found in the searched sources, so capex is left null rather than inferred from benchmarks. Fixed O&M was estimated from the 2024 AEMO/Aurecon OCGT large-unit parameter ($14,066/MW-net-year) and scaled to 188 MW. Variable O&M used the 2024 AEMO/Aurecon OCGT large-unit parameter ($4.68/MWh-net).