Avonlie Solar Farm (AVLSF1)

Solar · Iberdrola Australia Limited · Solar PV - Single axis tracking

Operational AEMO: In Service NSW1 Solar - Solar NEM data · 24 hours
254 MW
Registered nameplate capacity
24 hours revenue
$45.9k
Capacity factor
14.8%
Revenue / MWh
$50.80
Est. SRMC
$0.00/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
254 MW

AEMO status In Service
Project status Operational (AI)

Iberdrola Australia asset page (2024/2026) states siteworks began in early Q4 2021 and initial energisation was reached before end-2022; Power Technology says commercial operation in 2023.

Region NSW1
Coordinates

Site identified as Narrandera, NSW on Iberdrola Australia and Beon Energy project pages; precise plant coordinates not found in provided sources.

MLF 0.8698
DUID AVLSF1
Owner Iberdrola Australia Limited
Commissioned Nov 2023
Expected closure 2058
Closure date
Technology Solar PV - Single axis tracking
Fuel Solar - Solar
Module OEM Power Electronics
Module / inverter supplier PV modules / NEXTracker tracking system
Inverter OEM Power Electronics
Inverter model PCS / inverter platform (model not documented)
Equipment confidence high
Stats window
12 Jun 2026 00:00 → 12 Jun 2026 23:59 AEST

Dispatch & revenue

12 Jun 2026 00:00 → 12 Jun 2026 23:59 AEST

Energy revenue (× MLF)
$45.9k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
903.8 MWh
Available
903.8 MWh
Curtailed
MWh
Curtailment
0.0%
of available
MLF used
0.8698
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.8446
2025-07-01 0.8698

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (tracking)
Capacity
254 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$325.52M

Shown in table
$325.52M (2026 real AUD)

Reported / source value
$250.00M (2019 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Project-specific greenfield construction cost estimate for Avonlie Solar Farm.

Reference
Avonlie Solar Farm Project – Economic Impact Assessment (high confidence)
Source recorded 05 Jun 2026

Capex refurbishment
Capex / MW derived
$1,281,074

Shown in table
$1.28M (2026 real AUD)

Reported / source value
$983.9k (2019 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$8.14M

Shown in table
$8.14M (2026 real AUD)

Reported / source value
$6.24M (2019 nominal)
Table total may differ if recalculated from $/MW × registered capacity after CPI adjustment.

Fixed OPEX / MW-yr
$32,031

Shown in table
$32.0k (2026 real AUD)

Reported / source value
$24.6k (2019 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Reference annual O&M cost used to infer a per-MW-year fixed OPEX fallback.

Reference
2024 Energy Technology Cost and Technical Parameter Review Report - Solar (medium confidence)
Source recorded 05 Jun 2026

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2019 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 05 Jun 2026

Notes
Plant-specific greenfield construction cost was found in a project economic impact assessment provided to NSW planning: approximately A$250 million for the Avonlie Solar Farm project, attributed to RES. Iberdrola's 2021 announcement confirms final investment decision and states Avonlie is part of nearly A$1 billion of capital commitments across Avonlie, Port Augusta Renewable Energy Park, and Wallgrove Grid Battery; however, that figure is portfolio-level, not Avonlie-specific. O&M was not found as plant-specific data, so a benchmark-style estimate from AEMO/CSIRO large-scale solar PV assumptions was used as a fallback. The project is single-axis tracking; fixed OPEX per MW-year was inferred from the AEMO solar PV report's 40MW hypothetical project annual O&M cost ($624,000) divided by 40MW.

Sources