Ceduna BESS

BESS · tetrisenergy_nr · Storage - Battery

Development AEMO: Publicly Announced Other - Other NEM data · 24 hours
25/200 MW
Researched capacity / storage
Est. SRMC
$1.50/MWh
Key information
Capacity (AI)
25 MW / 200 MWh

AEMO spreadsheet / provided project data: 25.00 MW and 200.00 MWh storage.

AEMO status Publicly Announced
Project status Development (AI)

Based on the site being listed only as "Publicly Announced" and no evidence provided of construction, commissioning, or operation.

Coordinates

DUID
Owner tetrisenergy_nr
Commissioned
Expected closure
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM
Battery platform / chemistry
Inverter OEM
Inverter / PCS model
Stats window
13 Jun 2026 22:05 → 14 Jun 2026 22:05 AEST

Dispatch & revenue

13 Jun 2026 22:05 → 14 Jun 2026 22:05 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
25 MW / 200 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.50/MWh
Capex total (greenfield)
$73.84M

Shown in table
$73.84M (2026 real AUD)

Reported / source value
$70.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex refurbishment
Capex / MWh storage derived
$369,198

Shown in table
$369.2k (2026 real AUD)

Reported / source value
$350.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$25,000

Shown in table
$25.0k (2026 real AUD)

Variable OPEX / MWh default
$1.50

Shown in table
$1.50 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: low · Status: ai estimated · Capex basis: default · AI checked 06 Jun 2026

Notes
I could verify the site identity, owner, technology, and capacity from NEMStats and AEMO, but I could not find a plant-specific greenfield investment/capex announcement or official operating-cost assumptions for Ceduna BESS. No refurbishment information found. Capacity is 25 MW / 200 MWh.

Sources