Wattle Point (WPWF)

Wind · Infrastructure Capital Group · Wind Turbine - Onshore

Operational AEMO: In Service SA1 Wind - Wind NEM data · 24 hours
91 MW
Registered nameplate capacity
24 hours revenue
$36.3k
Capacity factor
29.2%
Revenue / MWh
$57.05
Est. SRMC
$0.50/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. SA1 regional price (RRP) on right axis.

Key information
Capacity
91 MW

AEMO status In Service
Project status Operational (AI)

The Wind Power database lists Wattle Point as an operational onshore wind farm commissioned in 2005.

Region SA1
Coordinates -35.13725, 137.69769 (AI)

The Wind Power lists coordinates for Wattle Point Wind Farm as 35° 8' 14.1" S, 137° 41' 51.7" E; AGL says it is 3 km southwest of Edithburgh, SA.

MLF 0.8476
DUID WPWF
Owner Infrastructure Capital Group
Commissioned
Expected closure 2031
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM Vestas
Turbine model V82/1650
Equipment confidence high
Stats window
22 Jul 2026 00:00 → 22 Jul 2026 23:59 AEST

Dispatch & revenue

22 Jul 2026 00:00 → 22 Jul 2026 23:59 AEST

Energy revenue (× MLF)
$36.3k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
636.5 MWh
Available
636.5 MWh
Curtailed
MWh
Curtailment
0.0%
of available
MLF used
0.8476
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • State of chargeINITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.8179
2025-07-01 0.8456
2026-07-01 0.8476

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
91 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.50/MWh
Capex total (greenfield) default
$199.65M

Shown in table
$199.65M (2026 real AUD)

Capex refurbishment
Capex / MW default
$2,200,000

Shown in table
$2.20M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

Variable OPEX / MWh default
$0.50

Shown in table
$0.50 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: unknown · Status: needs review · Capex basis: unknown