BESS · Quorn Park Solar Farm Pty Ltd as the trustee for Quorn Park Solar Farm Trust · Storage - Battery
Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.
20 Sep 2026 00:00 → 20 Sep 2026 09:50 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
Stored energy at the start of each 5‑minute interval (AEMO INITIAL_ENERGY_STORAGE).
Available up to the latest next‑day dispatch file.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.INITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.| Effective from | MLF |
|---|---|
| 2026-01-20 | 1.0190 |
| 2026-02-03 | 1.0190 |
| 2026-07-01 | 0.9032 |
| Capex total (greenfield) |
$200.42M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage derived |
$5,010,549
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$727.8k
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$26,371
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$1.58
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Plant-specific project webpage states construction with an investment value of over $190 million and operational target in 2026. The project is a hybrid solar + BESS facility; however, the provided DUID capacity (27.6 MW / 40 MWh) does not match the public project page capacity (98 MW solar / 20 MW BESS) or the original NSW assessment report (80 MW solar / 20 MW / 20 MWh BESS). Capex is therefore treated as reported project-level investment, not a DUID-specific battery-only cost, and capex per MW is a rough allocation using the provided 27.6 MW capacity.