Quorn Park Solar Hybrid (QPBESS)

BESS · Quorn Park Solar Farm Pty Ltd as the trustee for Quorn Park Solar Farm Trust · Storage - Battery

Development AEMO: Committed NSW1 Other - Other NEM data · 4h
28/40 MW
Registered nameplate capacity / storage
Est. SRMC
$1.58/MWh
Key information
Capacity
28 MW / 40 MWh

AEMO status Committed
Project status Development (AI)

Region NSW1
Coordinates

DUID QPBESS
Owner Quorn Park Solar Farm Pty Ltd as the trustee for Quorn Park Solar Farm Trust
Commissioned Jan 2026
Expected closure 2045
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM
Battery platform / chemistry
Inverter OEM
Inverter / PCS model
Stats window
14 Jun 2026 00:00 → 14 Jun 2026 04:05 AEST

Dispatch & revenue

14 Jun 2026 00:00 → 14 Jun 2026 04:05 AEST

No dispatch data for DUID QPBESS in this period.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
28 MW / 40 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.58/MWh
Capex total (greenfield)
$200.42M

Shown in table
$200.42M (2026 real AUD)

Reported / source value
$190.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
INPEX confirms FID for the project and supports the project-level scale, but the press release excerpt available here does not state the dollar amount directly.

Reference
オーストラリア ニューサウスウェールズ州におけるQuorn Park 太陽光・蓄電池プロジェクトの最終投資決定について (medium confidence)
Source recorded 06 Jun 2026

Capex refurbishment
Capex / MWh storage derived
$5,010,549

Shown in table
$5.01M (2026 real AUD)

Reported / source value
$4.75M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$727.8k

Shown in table
$727.8k (2026 real AUD)

Reported / source value
$687.5k (2024 nominal)
Table total may differ if recalculated from $/MW × registered capacity after CPI adjustment.

Fixed OPEX / MW-yr
$26,371

Shown in table
$26.4k (2026 real AUD)

Reported / source value
$25.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No project-specific battery O&M source was found, so the provided fallback default was used.

Variable OPEX / MWh
$1.58

Shown in table
$1.58 (2026 real AUD)

Reported / source value
$1.50 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No project-specific variable O&M source was found, so the provided fallback default was used.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Plant-specific project webpage states construction with an investment value of over $190 million and operational target in 2026. The project is a hybrid solar + BESS facility; however, the provided DUID capacity (27.6 MW / 40 MWh) does not match the public project page capacity (98 MW solar / 20 MW BESS) or the original NSW assessment report (80 MW solar / 20 MW / 20 MWh BESS). Capex is therefore treated as reported project-level investment, not a DUID-specific battery-only cost, and capex per MW is a rough allocation using the provided 27.6 MW capacity.