Millmerran Power Plant (MPP_2)

Coal · Millmerran Power Partners · Turbine - Steam Super Critical

Operational AEMO: In Service QLD1 Fossil - Black Coal NEM data · 19h
426 MW
Registered nameplate capacity
19h revenue
$103.1k
Capacity factor
29.6%
Revenue / MWh
$42.98
Est. SRMC
$52.60/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
426 MW

AEMO status In Service
Project status Operational (AI)

DL Energy project page (commercial operation February 2003) and GEM/plant profile showing operating status.

Region QLD1
Coordinates -27.96070, 151.27930 (AI)

Global Energy Monitor / Wikipedia coordinates for Millmerran power station.

MLF 0.9800
DUID MPP_2
Owner Millmerran Power Partners
Commissioned
Expected closure 2051
Closure date
Technology Turbine - Steam Super Critical
Fuel Fossil - Black Coal
Steam turbine OEM Doosan Škoda Power
Turbine / boiler supplier Boiler supplier not found; likely Mitsubishi Heavy Industries or equivalent supercritical boiler EPC
Equipment confidence low
Stats window
13 Jun 2026 00:00 → 13 Jun 2026 19:15 AEST

Dispatch & revenue

13 Jun 2026 00:00 → 13 Jun 2026 19:15 AEST

Energy revenue (× MLF)
$103.1k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
2,398.5 MWh
Available
1,776.2 MWh
Curtailed
MWh
Curtailment
0.0%
of available
MLF used
0.9800
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9797
2025-07-01 0.9800

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Black coal
Capacity
426 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$52.60/MWh
Capex total (greenfield) default
$1,491.00M

Shown in table
$1,491.00M (2026 real AUD)

Capex refurbishment
Capex / MW default
$3,500,000

Shown in table
$3.50M (2026 real AUD)

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$55,000

Shown in table
$55.0k (2026 real AUD)

Variable OPEX / MWh default
$4.00

Shown in table
$4.00 (2026 real AUD)

Fuel cost / GJ default
$4.50

Shown in table
$4.50 (2026 real AUD)

Heat rate GJ/MWh default
10.80

Shown in table
$10.80 (2026 real AUD)

Confidence: unknown · Status: needs review · Capex basis: unknown