Hallett GT (AGLHAL)

Gas Peakers · EnergyAustralia Hallett Pty Ltd · Turbine - OCGT

Operational AEMO: In Service SA1 Fossil - Natural Gas Pipeline NEM data · 18h
277 MW
Registered nameplate capacity
18h revenue
$0
Capacity factor
0.0%
Revenue / MWh
Est. SRMC
$100.22/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. SA1 regional price (RRP) on right axis.

Key information
Capacity
277 MW

AEMO status In Service
Project status Operational (AI)

EnergyAustralia Hallett Power Station page describes the station as an existing peaking asset; GEO/Wikipedia show it was commissioned in 2001/2002 and is in service.

Region SA1
Coordinates -33.34870, 138.75170 (AI)

Global Energy Observatory profile for AGL Hallett OCGT Power Plant lists coordinates at Hallett, Canowie, South Australia.

MLF 0.9663
DUID AGLHAL
Owner EnergyAustralia Hallett Pty Ltd
Commissioned
Expected closure 2036
Closure date
Technology Turbine - OCGT
Fuel Fossil - Natural Gas Pipeline
Gas turbine OEM GE Vernova
Turbine / engine model LM6000
Equipment confidence medium
Stats window
13 Jun 2026 00:00 → 13 Jun 2026 17:50 AEST

Dispatch & revenue

13 Jun 2026 00:00 → 13 Jun 2026 17:50 AEST

Energy revenue (× MLF)
$0
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
MWh
Available
673.7 MWh
Curtailed
673.7 MWh
Curtailment
100.0%
of available
MLF used
0.9663
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9565
2025-07-01 0.9663

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
OCGT
Capacity
277 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$100.22/MWh
Capex total (greenfield)
$123.42M

Shown in table
$123.42M (2026 real AUD)

Reported / source value
$117.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
This is a transaction price, not plant construction capex, so it was not used as capex_total_aud.

Reference
Our history | EnergyAustralia (high confidence)
Source recorded 08 Jun 2026

Capex refurbishment
Capex / MW derived
$445,777

Shown in table
$445.8k (2026 real AUD)

Reported / source value
$422.6k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$4.11M

Shown in table
$4.11M (2026 real AUD)

Reported / source value
$3.89M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$14,838

Shown in table
$14.8k (2026 real AUD)

Reported / source value
$14.1k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used as the OCGT fixed O&M benchmark.

Reference
2023 Cost and Technical Parameters Review (high confidence)
Source recorded 08 Jun 2026

Variable OPEX / MWh
$4.94

Shown in table
$4.94 (2026 real AUD)

Reported / source value
$4.68 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used as the OCGT variable O&M benchmark.

Reference
2024 Energy Technology Cost and Technical Parameter Review (high confidence)
Source recorded 08 Jun 2026

Fuel cost / GJ default
$12.00

Shown in table
$12.00 (2026 real AUD)

Heat rate GJ/MWh
7.94

Shown in table
$7.94 (2026 real AUD)

How this was derived
Used as the OCGT heat-rate benchmark.

Reference
2023 Cost and Technical Parameters Review (high confidence)
Source recorded 08 Jun 2026

Confidence: medium · Status: ai estimated · Capex basis: estimated · AI checked 08 Jun 2026

Notes
No project-specific greenfield capex announcement for Hallett GT was found in the searched sources. The plant is an existing gas-fired station built in 2001 and has an installed capacity of 235 MW on the owner site, while the requested DUID capacity is 276.86 MW; the difference suggests the DUID may represent aggregated or differently scoped units/site naming. O&M and thermal performance were benchmarked from AEMO/Aurecon OCGT reference data; fuel cost was not directly sourced.

Sources