Golden Plains Wind Farm West (GPWFWST2)

Wind · Golden Plains WF2 Unit Trust · Wind Turbine - Onshore

Development AEMO: Committed VIC1 Wind - Wind NEM data · 24 hours
557 MW
Registered nameplate capacity
24 hours revenue
$149.5k
Capacity factor
13.7%
Revenue / MWh
$81.72
Est. SRMC
$0.53/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. VIC1 regional price (RRP) on right axis.

Key information
Capacity
557 MW

AEMO status Committed
Project status Development (AI)

Region VIC1
Coordinates —

MLF 0.9823
DUID GPWFWST2
Owner Golden Plains WF2 Unit Trust
Commissioned Feb 2027
Expected closure 2057
Closure date —
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM —
Turbine model —
Stats window
24 Sep 2026 19:30 → 25 Sep 2026 19:30 AEST

Dispatch & revenue

24 Sep 2026 19:30 → 25 Sep 2026 19:30 AEST

Energy revenue (× MLF)
$149.5k
FCAS revenue (× MLF)
$0
FCAS volume
— MWh
Dispatched
1,829.7 MWh
Available
1,607.6 MWh
Curtailed
— MWh
Curtailment
0.0%
of available
MLF used
0.9823
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional price — dispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • State of charge — INITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2026-01-20 0.9837
2026-07-01 0.9823

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
557 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.53/MWh
Capex total (greenfield)
$4,219.41M

Shown in table
$4,219.41M (2026 real AUD)

Reported / source value
$4,000.00M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Confirms Stage 2 / West is part of the larger 1,333 MW mega-project, but does not give a West-only AUD cost.

Reference
Ingka Investments secures 15% of Stage 2 in southern hemisphere’s largest wind farm (medium confidence)
Source recorded 08 Jun 2026

Capex refurbishment
—
Capex / MW derived
$7,574,289

Shown in table
$7.57M (2026 real AUD)

Reported / source value
$7.18M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$32.32M

Shown in table
$32.32M (2026 real AUD)

Reported / source value
$30.69M (2024 nominal)
Table total may differ if recalculated from $/MW × registered capacity after CPI adjustment.

How this was derived
Server-side fallback default used because no plant-specific onshore wind O&M cost was found.

Fixed OPEX / MW-yr
$58,017

Shown in table
$58.0k (2026 real AUD)

Reported / source value
$55.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Variable OPEX / MWh
$0.53

Shown in table
$0.53 (2026 real AUD)

Reported / source value
$0.50 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Server-side fallback default used because no plant-specific onshore wind variable O&M cost was found.

Fuel cost / GJ
—
Heat rate GJ/MWh
—

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 08 Jun 2026

Notes
Reported project cost for the full Golden Plains Wind Farm appears to be about A$4 billion, with sources describing Golden Plains as a 1,333 MW project and Stage 2/West as part of the larger development. West stage construction commenced in mid-2024 and is described as ~574 MW / 577 MW in project materials; the owner/developer sources did not provide a separate West-only capital cost, so the full-project reported cost was allocated to this site as the best available plant-level proxy. O&M values were not plant-specific, so server defaults were used for wind onshore.

Sources