Coal · Gladstone Power Station Participants · Turbine - Steam Sub Critical
Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.
13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.| Effective from | MLF |
|---|---|
| 2024-07-01 | 0.9403 |
| 2025-07-01 | 0.9461 |
| Capex total (greenfield) |
$1,033.76M
Shown in table Reported / source value |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$3,691,983
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$69.57M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$248,477
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$14.55
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ default |
$4.50
Shown in table |
| Heat rate GJ/MWh |
8.98
Shown in table How this was derived Reference |
Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 07 Jun 2026
Notes
Gladstone Power Station was officially opened in September 1976; the plant’s unit sizes are 280 MW. AEMO/Aurecon 2024 review provides a generic black-coal new entrant heat rate of 8.98 GJ/MWh and availability assumptions for Australian black coal plants; the same review also contains a generic sub-critical boiler O&M example, which is used here only as a fallback proxy because plant-specific O&M was not located. Capex is left null because no plant-specific original construction cost source was found in the searched official and owner sources.