Solar · Spark Renewables Pty Ltd · Solar PV - Single axis tracking
13 Jun 2026 01:10 → 14 Jun 2026 01:10 AEST
| Capex total (greenfield) |
$1,350.00M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$4,500,000
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX (annual) |
$6.00M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$20,000
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$0.25
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
$0.00
Shown in table Reported / source value |
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026
Notes
Plant-specific planning/approval sources indicate an estimated development cost of $1.35 billion for the Dinawan Solar Farm element of the broader Dinawan Energy Hub. The figure appears to cover the ~800 MW solar farm plus 356 MW/1,574 MWh BESS, so it likely overstates the 300 MW solar-only allocation used here; capex_per_mw is therefore a simple allocation of the reported project cost to the 300 MW unit and should be treated cautiously. No separate owner-reported greenfield capex for the 300 MW solar tranche was found in search results.