Darlington Point Solar Farm (DARLSF1)

Solar · Darlington Point Solar Farm Pty Ltd · Solar PV - Single axis tracking

Operational AEMO: In Service NSW1 Solar - Solar NEM data · 24 hours
275 MW
Registered nameplate capacity
24 hours revenue
$1.7k
Capacity factor
0.8%
Revenue / MWh
$32.30
Est. SRMC
$0.33/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
275 MW

AEMO status In Service
Project status Operational (AI)

NSW Planning Portal SSD-8392 modification (2022): project has completed construction and is now operational and exporting electricity to the grid.

Region NSW1
Coordinates

Site described as approximately 10 km south of Darlington Point town centre on the banks of the Murrumbidgee River (Spiire; Nilsen).

MLF 0.8854
DUID DARLSF1
Owner Darlington Point Solar Farm Pty Ltd
Commissioned Apr 2021
Expected closure 2055
Closure date
Technology Solar PV - Single axis tracking
Fuel Solar - Solar
Module OEM Canadian Solar
Module / inverter supplier Canadian Solar / SMA Solar Technology
Inverter OEM SMA Solar Technology
Inverter model Sunny Central / PCU skid units
Equipment confidence high
Stats window
12 Jun 2026 22:55 → 13 Jun 2026 22:55 AEST

Dispatch & revenue

12 Jun 2026 22:55 → 13 Jun 2026 22:55 AEST

Energy revenue (× MLF)
$1.7k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
54.2 MWh
Available
MWh
Curtailed
MWh
Curtailment
of available
MLF used
0.8854
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.8439
2025-07-01 0.8854

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (tracking)
Capacity
275 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.33/MWh
Capex total (greenfield)
$595.24M

Shown in table
$595.24M (2026 real AUD)

Reported / source value
$450.00M (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Owner/developer financing announcement gives the project construction funding amount.

Reference
Octopus Investments and Edify Energy finance new $450 million solar farm (high confidence)
Source recorded 07 Jun 2026

Capex refurbishment
Capex / MW derived
$2,164,738

Shown in table
$2.16M (2026 real AUD)

Reported / source value
$1.64M (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated using reported project finance amount and site capacity.

Reference
Octopus Investments and Edify Energy finance new $450 million solar farm (medium confidence)
Source recorded 07 Jun 2026

Fixed OPEX (annual)
$7.27M

Shown in table
$7.27M (2026 real AUD)

Reported / source value
$5.50M (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated from fallback fixed O&M and capacity.

Fixed OPEX / MW-yr
$26,455

Shown in table
$26.5k (2026 real AUD)

Reported / source value
$20.0k (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No plant-specific fixed O&M source was found; internal default used as instructed.

Variable OPEX / MWh
$0.33

Shown in table
$0.33 (2026 real AUD)

Reported / source value
$0.25 (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No plant-specific variable O&M source was found; internal default used as instructed.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026

Notes
Greenfield project construction was financed at more than $450 million in December 2018. Site approval documents identify the project as a 275 MW solar farm with a 100 MWh BESS in the original consent, but the capex figure sourced here is for the solar farm project financing announcement and is treated as the project-level construction cost for the generator. Fixed O&M uses the provided fallback default of $20,000/MW-year; annual fixed O&M implied at 274.97 MW is about $5.5 million. No plant-specific O&M, fuel, heat-rate, or emissions data beyond zero direct emissions for solar PV were found in the searched sources.

Sources