Solar · Cultana Solar Project Company Pty Ltd as trustee for the Cultana Solar Farm Trust · Solar PV - Single axis tracking
06 Jun 2026 22:00 → 13 Jun 2026 22:00 AEST
| Capex total (greenfield) |
$455.73M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$1,274,945
Shown in table Reported / source value How this was derived |
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr default |
$20,000
Shown in table |
| Variable OPEX / MWh default |
$0.25
Shown in table |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026
Notes
Plant-specific reported greenfield capex found in public sources as $350 million for the 280 MW Cultana Solar Farm project announced/preparing for construction in 2019-2022 materials. Capacity used for per-MW calculation is the registered/project capacity provided (357.45 MW), so per-MW is an implied figure rather than the source's original capacity basis. No verified plant-specific fixed/variable O&M or fuel assumptions were found; solar PV has no fuel cost or heat rate, and emissions intensity is zero.