Crookwell 2 Wind Farm (CROOKWF2)

Wind · Crookwell Development Pty Ltd · Wind Turbine - Onshore

Operational AEMO: In Service NSW1 Wind - Wind NEM data · 7 days
96 MW
Registered nameplate capacity
7 days revenue
$198.3k
Capacity factor
16.9%
Revenue / MWh
$72.86
Est. SRMC
$0.69/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
96 MW

AEMO status In Service
Project status Operational (AI)

Tilt Renewables project page (2025): Crookwell 2 is operational and commissioned in 2018.

Region NSW1
Coordinates -34.51650, 149.54248 (AI)

Wikipedia coordinates for Crookwell Wind Farm / Crookwell II site area in Crookwell, NSW.

MLF 0.9644
DUID CROOKWF2
Owner Crookwell Development Pty Ltd
Commissioned Sep 2018
Expected closure 2043
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM GE
Turbine model 3.4-130
Equipment confidence high
Stats window
07 Jun 2026 00:20 → 14 Jun 2026 00:20 AEST

Dispatch & revenue

07 Jun 2026 00:20 → 14 Jun 2026 00:20 AEST

Energy revenue (× MLF)
$198.3k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
2,721.1 MWh
Available
2,472.7 MWh
Curtailed
MWh
Curtailment
0.0%
of available
MLF used
0.9644
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9512
2025-07-01 0.9644

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
96 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.69/MWh
Capex total (greenfield)
$244.48M

Shown in table
$244.48M (2026 real AUD)

Reported / source value
$177.00M (2016 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Direct project-specific greenfield investment announcement from the owner/developer.

Reference
Award of wind farm Crookwell II in Australia (high confidence)
Source recorded 07 Jun 2026

Capex refurbishment
Capex / MW derived
$2,545,555

Shown in table
$2.55M (2026 real AUD)

Reported / source value
$1.84M (2016 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated from reported total capex and registered capacity.

Reference
Award of wind farm Crookwell II in Australia (medium confidence)
Source recorded 07 Jun 2026

Fixed OPEX (annual)
$7.42M

Shown in table
$7.42M (2026 real AUD)

Reported / source value
$5.37M (2016 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Annual fixed O&M calculated from the per-MW benchmark and plant capacity.

Reference
2024 Energy Technology Cost and Technical Parameter Review (medium confidence)
Source recorded 07 Jun 2026

Fixed OPEX / MW-yr
$77,210

Shown in table
$77.2k (2026 real AUD)

Reported / source value
$55.9k (2016 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used as a fallback benchmark because site-specific O&M was not found. Value reflects an onshore wind benchmark used in AEMO/Aurecon technology-cost work.

Reference
2024 Energy Technology Cost and Technical Parameter Review (medium confidence)
Source recorded 07 Jun 2026

Variable OPEX / MWh
$0.69

Shown in table
$0.69 (2026 real AUD)

Reported / source value
$0.50 (2016 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No site-specific variable O&M located; retained provided default.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026

Notes
Project-specific reported construction investment was found for Crookwell II: GPG said it would invest over A$177 million in construction and associated investments. A separate project announcement described the development as a $200 million Crookwell 2 Wind Farm. I used the more direct owner/developer reported figure of A$177 million as the primary capex. Fixed O&M was not found for this site, so an onshore-wind benchmark was used as fallback; variable O&M set from internal default. Capex year reflects the 2016 award/announcement timing rather than the 2018 commissioning date.

Sources