Coppabella Wind Farm (COPBEL)

Wind · Coppabella Wind Farm Pty Ltd · Wind Turbine - Onshore

Development AEMO: Anticipated NSW1 Wind - Wind NEM data · 30 days
290 MW
Researched capacity
Est. SRMC
$0.00/MWh
Key information
Capacity (AI)
290 MW

AEMO spreadsheet entry for Coppabella Wind Farm (289.80 MW); no reliable public project page or approval result was returned in search.

AEMO status Anticipated
Project status Development (AI)

AEMO registration status is Anticipated and the project has a future commissioning date of 2027-09-01, indicating pre-construction/development rather than operational status.

Region NSW1
Coordinates

DUID COPBEL
Owner Coppabella Wind Farm Pty Ltd
Commissioned Sep 2027
Expected closure 2057
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM
Turbine model
Stats window
14 May 2026 14:05 → 13 Jun 2026 14:05 AEST

Dispatch & revenue

14 May 2026 14:05 → 13 Jun 2026 14:05 AEST

No dispatch data for DUID COPBEL in this period.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
290 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$275.06M

Shown in table
$275.06M (2026 real AUD)

Reported / source value
$260.76M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Older non-owner estimate that brackets project investment.

Reference
AWA submission to the public exhibition of the (low confidence)
Source recorded 07 Jun 2026

Capex refurbishment
Capex / MW derived
$949,149

Shown in table
$949.1k (2026 real AUD)

Reported / source value
$899.8k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$22.52M

Shown in table
$22.52M (2026 real AUD)

Reported / source value
$16.70M (2017 nominal)
Table total may differ if recalculated from $/MW × registered capacity after CPI adjustment.

Fixed OPEX / MW-yr
$77,703

Shown in table
$77.7k (2026 real AUD)

Reported / source value
$57.5k (2017 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used only as fallback basis for onshore wind O&M since no site-specific O&M was found.

Reference
2024 Energy Technology Cost and Technical Parameter Review (low confidence)
Source recorded 07 Jun 2026

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2017 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Wind variable O&M was not separately identified; set to zero for fallback consistency.

Reference
2024 Energy Technology Cost and Technical Parameter Review (low confidence)
Source recorded 07 Jun 2026

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026

Notes
Plant-specific construction-cost figure was not found as a full project total. The only explicit owner-project value located in current project documents was a total project contract value of $260.76 million tied to local content commitments; this is not clearly stated as total greenfield CAPEX, so it has been used as the closest reported project value with low-to-medium confidence and should be reviewed. No refurbishment cost found. For operating assumptions, onshore wind defaults were applied as project-specific O&M was not found. The project website states the current layout is ~289 MW / 289.8 MW nameplate and owned by Goldwind Australia, with construction and operation managed by Goldwind Australia Pty Ltd.