Condamine A (CPSA)

Coal · QGC Sales QLD Pty Ltd · Turbine - CCGT

Operational AEMO: In Service QLD1 Fossil - Coal Seam Methane NEM data · 24 hours
87 MW
Registered nameplate capacity
24 hours revenue
$0
Capacity factor
0.0%
Revenue / MWh
Est. SRMC
$95.40/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
87 MW

AEMO status In Service
Project status Operational (AI)

Global Energy Monitor 2023 / Wikipedia: Condamine Power Station described as an operating 140 MW combined-cycle power station.

Region QLD1
Coordinates -26.66360, 150.26500 (AI)

Wikidata/Wikipedia coordinates for Condamine Power Station near Miles, Queensland.

MLF 0.9724
DUID CPSA
Owner QGC Sales QLD Pty Ltd
Commissioned
Expected closure 2039
Closure date
Technology Turbine - CCGT
Fuel Fossil - Coal Seam Methane
Equipment OEM Austrian Energy & Environment
Equipment type / model combined-cycle gas turbine power station (140 MW net)
Secondary OEM likely GE or Siemens
Secondary equipment CCGT turbine package / steam turbine-generator package
Equipment confidence medium
Stats window
13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST

Dispatch & revenue

13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST

Energy revenue (× MLF)
$0
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
MWh
Available
MWh
Curtailed
MWh
Curtailment
of available
MLF used
0.9724
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9729
2025-07-01 0.9724

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
CCGT
Capacity
87 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$95.40/MWh
Capex total (greenfield)
$270.70M

Shown in table
$270.70M (2026 real AUD)

Reported / source value
$170.00M (2008 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Reported plant-specific project cost for Condamine Power Station / Condamine A development.

Reference
AGL Energy Limited announcement re QGC transaction (high confidence)
Source recorded 07 Jun 2026

Capex refurbishment
Capex / MW derived
$3,097,261

Shown in table
$3.10M (2026 real AUD)

Reported / source value
$1.95M (2008 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$1.96M

Shown in table
$1.96M (2026 real AUD)

Reported / source value
$1.23M (2008 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$22,398

Shown in table
$22.4k (2026 real AUD)

Reported / source value
$14.1k (2008 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used as fallback fixed O&M benchmark for large CCGT.

Reference
2024 Energy Technology Cost and Parameters Review (high confidence)
Source recorded 07 Jun 2026

Variable OPEX / MWh
$12.90

Shown in table
$12.90 (2026 real AUD)

Reported / source value
$8.10 (2008 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Used as fallback variable O&M benchmark for large CCGT.

Reference
2024 Energy Technology Cost and Parameters Review (high confidence)
Source recorded 07 Jun 2026

Fuel cost / GJ default
$11.00

Shown in table
$11.00 (2026 real AUD)

Heat rate GJ/MWh default
7.50

Shown in table
$7.50 (2026 real AUD)

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026

Notes
Plant-specific capital cost was found in a QGC/AGL announcement: exercise price for Condamine Power Station to be the higher of costs paid up to completion, currently estimated at A$170 million. The source refers to the 140 MW project under construction in 2008, while the registered unit capacity is 87.4 MW, so capex per MW is based on the provided DUID capacity. AEMO 2024 CCGT benchmark O&M values were used as fallback for operating cost assumptions.

Sources