Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.
14 May 2026 16:45 → 13 Jun 2026 16:45 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.| Effective from | MLF |
|---|---|
| 2024-07-01 | 0.9356 |
| 2025-07-01 | 0.9413 |
| Capex total (greenfield) |
$138.12M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$3,249,919
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$1.06M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$24,862
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$0.28
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Project sources consistently describe Collinsville Solar PV as a $100 million / ~$97.2 million project for 42.5 MW. The cited reported figure used here is $100 million nominal. No refurbishment cost identified.