Coleambally Solar Farm (COLEASF1)

Solar · Coleambally Solar Pty Ltd · Solar PV - Single axis tracking

Operational AEMO: In Service NSW1 Solar - Solar NEM data · 30 days
150 MW
Registered nameplate capacity
30 days revenue
$613.9k
Capacity factor
11.1%
Revenue / MWh
$50.92
Est. SRMC
$0.00/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
150 MW

AEMO status In Service
Project status Operational (AI)

GlobalData / Power Technology 2024: construction commenced in 2018 and the project entered commercial operation in November 2018.

Region NSW1
Coordinates

Wikipedia and project pages place the site near Coleambally, NSW, west of Kidman Way north of town, but no precise coordinates were found in the provided results.

MLF 0.8730
DUID COLEASF1
Owner Coleambally Solar Pty Ltd
Commissioned
Expected closure 2043
Closure date
Technology Solar PV - Single axis tracking
Fuel Solar - Solar
Module OEM Schneider Electric
Module / inverter supplier module / inverter supplier
Inverter OEM Schneider Electric
Inverter model inverter model not documented
Equipment confidence high
Stats window
15 May 2026 02:50 → 14 Jun 2026 02:50 AEST

Dispatch & revenue

15 May 2026 02:50 → 14 Jun 2026 02:50 AEST

Energy revenue (× MLF)
$613.9k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
12,057.2 MWh
Available
12,112.6 MWh
Curtailed
82.2 MWh
Curtailment
0.7%
of available
MLF used
0.8730
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.8367
2025-07-01 0.8730

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar (tracking)
Capacity
150 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$264.55M

Shown in table
$264.55M (2026 real AUD)

Reported / source value
$200.00M (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Project-specific greenfield investment cost for the Coleambally Solar Farm.

Reference
Coleambally Solar Farm, New South Wales (medium confidence)
Source recorded 06 Jun 2026

Capex refurbishment
Capex / MW derived
$1,760,148

Shown in table
$1.76M (2026 real AUD)

Reported / source value
$1.33M (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Derived per-MW capex from reported total cost and registered capacity.

Reference
Coleambally Solar Farm, New South Wales (medium confidence)
Source recorded 06 Jun 2026

Fixed OPEX (annual)
$2.39M

Shown in table
$2.39M (2026 real AUD)

Reported / source value
$1.80M (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Annual fixed O&M derived from benchmark and capacity.

Reference
2024 Energy Technology Cost and Technical Parameter Review Report - Solar (high confidence)
Source recorded 06 Jun 2026

Fixed OPEX / MW-yr
$15,873

Shown in table
$15.9k (2026 real AUD)

Reported / source value
$12.0k (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Solar PV fixed O&M benchmark used as fallback.

Reference
2024 Energy Technology Cost and Technical Parameter Review Report - Solar (high confidence)
Source recorded 06 Jun 2026

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2018 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Project commenced construction in January 2018 and entered full-scale commercial operation in November 2018. Plant-specific capital cost was reported as more than A$200 million; this was used as the best available project-level greenfield cost. Operating life is commonly described by the owner as 25 years of affordable clean power, while Neoen said expected service life is well beyond 30 years; asset_life_years set to 30 as a conservative planning assumption.

Sources