Clarke Creek Wind Farm (CLRKCWF2)

Wind · Squadron Energy Services Pty Ltd · Wind Turbine - Onshore

Commissioning AEMO: In Commissioning QLD1 Wind - Wind NEM data · 30 days
104 MW
Registered nameplate capacity
30 days revenue
$2.07M
Capacity factor
37.0%
Revenue / MWh
$75.16
Est. SRMC
$0.58/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
104 MW

AEMO status In Commissioning
Project status Commissioning (AI)

AEMO listing says 'In Commissioning'; Squadron Energy project page indicates OSOM deliveries and next-phase works, consistent with commissioning/buildout in 2025.

Region QLD1
Coordinates -22.95000, 148.35000 (AI)

Approximate Clarke Creek project area near Clarke Creek, Queensland (project website / public references); precise turbine coordinates not published in provided results.

MLF 0.9430
DUID CLRKCWF2
Owner Squadron Energy Services Pty Ltd
Commissioned Sep 2025
Expected closure 2049
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM
Turbine model
Equipment confidence low
Stats window
15 May 2026 06:20 → 14 Jun 2026 06:20 AEST

Dispatch & revenue

15 May 2026 06:20 → 14 Jun 2026 06:20 AEST

Energy revenue (× MLF)
$2.07M
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
27,564.4 MWh
Available
27,810.8 MWh
Curtailed
303.3 MWh
Curtailment
1.1%
of available
MLF used
0.9430
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2025-04-23 0.9497
2025-07-01 0.9430

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
104 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.58/MWh
Capex total (greenfield)
$1,318.41M

Shown in table
$1,318.41M (2026 real AUD)

Reported / source value
$1,060.00M (2021 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Official reported capital expenditure for Clarke Creek Wind Farm Stage 1.

Reference
Clarke Creek Wind Farm (Stage 1) - Australian Industry Participation Plan Summary (high confidence)
Source recorded 06 Jun 2026

Capex refurbishment
Capex / MW derived
$12,738,241

Shown in table
$12.74M (2026 real AUD)

Reported / source value
$10.24M (2021 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Calculated using the reported capex and the user-provided DUID capacity of 103.5 MW.

Reference
Clarke Creek Wind Farm (Stage 1) - Australian Industry Participation Plan Summary (medium confidence)
Source recorded 06 Jun 2026

Fixed OPEX (annual)
$6.65M

Shown in table
$6.65M (2026 real AUD)

Reported / source value
$5.69M (2022 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$64,252

Shown in table
$64.3k (2026 real AUD)

Reported / source value
$55.0k (2022 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Internal default used because no plant-specific fixed O&M source was found in the web search.

Variable OPEX / MWh
$0.58

Shown in table
$0.58 (2026 real AUD)

Reported / source value
$0.50 (2022 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Internal default used because no plant-specific variable O&M source was found in the web search.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026

Notes
Plant-specific greenfield capex was found in an official Australian Industry Participation summary for Clarke Creek Wind Farm Stage 1. The project later secured $1 billion financing and stage one is a 450 MW project, but the reported capital expenditure used here is the official project capex figure from the 2021 AIP summary. Because the public source is for Stage 1, capex per MW is calculated using the registered DUID capacity of 103.5 MW as requested, which likely overstates unit cost if the $1.06 billion figure is for the broader stage-one project rather than this DUID alone.