Solar · Clare Asset Co Pty Ltd ATF Clare Asset Trust · Solar PV - Single axis tracking
Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.
15 May 2026 02:50 → 14 Jun 2026 02:50 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.| Effective from | MLF |
|---|---|
| 2024-07-01 | 0.9116 |
| 2025-07-01 | 0.9363 |
| Capex total (greenfield) |
$262.43M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$2,377,092
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX (annual) |
$4.27M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$38,674
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$0.00
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
How this was derived Reference |
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 06 Jun 2026
Notes
Project-specific EPC contract value of $190 million was reported in December 2016 for the 100 MW Clare Solar Farm; this is used as a proxy for greenfield CAPEX because a plant-specific total project cost announcement was not found. The site is a utility-scale single-axis tracking PV plant. Fixed O&M uses an AEMO/Aurecon benchmark for utility-scale solar PV; variable O&M is treated as nil for solar. Capacity used for per-MW calculation is the registered 110.4 MW supplied by the user, so the per-MW figure is an approximation rather than the original contract capacity basis.