Christies Beach Wastewater Treatment Plant (CBWWBA1)

BESS · South Australian Water Corporation · Storage - Battery

Commissioning AEMO: In Commissioning SA1 Other - Other NEM data · 24 hours
2/4 MW
Registered nameplate capacity / storage
24 hours revenue
$378
Capacity factor
1.8%
Revenue / MWh
$415.62
Est. SRMC
$1.50/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. SA1 regional price (RRP) on right axis.

Key information
Capacity
2 MW / 4 MWh

AEMO status In Commissioning
Project status Commissioning (AI)

ESCOSA variation application for SA Water Christies Beach site describes a battery storage plant; AEMO spreadsheet says In Commissioning, but project phase inferred from project context and stage timing.

Region SA1
Coordinates

MLF 1.0033
DUID CBWWBA1
Owner South Australian Water Corporation
Commissioned Jan 2023
Expected closure 2041
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM
Battery platform / chemistry Battery / BESS
Inverter OEM
Inverter / PCS model
Equipment confidence low
Stats window
22 Jul 2026 05:50 → 23 Jul 2026 05:50 AEST

Dispatch & revenue

22 Jul 2026 05:50 → 23 Jul 2026 05:50 AEST

Energy revenue (× MLF)
$378
FCAS revenue (× MLF)
$1
FCAS volume
0.3 MWh
Dispatched
0.9 MWh
Available
44.7 MWh
Curtailed
43.8 MWh
Curtailment
98.0%
of available
MLF used
1.0033
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

🔋 State of charge

Stored energy at the start of each 5‑minute interval (AEMO INITIAL_ENERGY_STORAGE). Available up to the latest next‑day dispatch file.

0.7 MWh 16%
at 23 Jul 04:00 · of 4 MWh registered

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • State of chargeINITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-09-06 1.0025
2025-07-01 1.0037
2026-07-01 1.0033

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
2 MW / 4 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.50/MWh
Capex total (greenfield)
$1.59M

Shown in table
$1.59M (2026 real AUD)

Reported / source value
$1.51M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex refurbishment
Capex / MWh storage derived
$369,198

Shown in table
$369.2k (2026 real AUD)

Reported / source value
$350.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
Fixed OPEX / MW-yr default
$25,000

Shown in table
$25.0k (2026 real AUD)

Variable OPEX / MWh default
$1.50

Shown in table
$1.50 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: low · Status: ai estimated · Capex basis: default · AI checked 06 Jun 2026

Notes
No plant-specific public source for the Christies Beach Wastewater Treatment Plant battery construction cost, O&M, or performance parameters was found in the searched official SA Water sources. SA Water does state it has installed solar panels and battery storage on some existing land and facilities as part of its Zero-Cost Energy Future program, but the searched results did not identify this DUID's battery project cost or a battery-specific asset breakdown for Christies Beach. The site is part of SA Water's broader wastewater operations; the plant itself began operating in 1970 and was significantly upgraded in 2013. Because no verified plant-specific capex was found, no capex estimate was substituted.

Sources