12 Jun 2026 21:15 → 13 Jun 2026 21:15 AEST
| Capex total (greenfield) |
$9.28M
Shown in table Reported / source value |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$4,219,409
Shown in table Reported / source value |
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr default |
$40,000
Shown in table |
| Variable OPEX / MWh default |
$1.00
Shown in table |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: default · AI checked 06 Jun 2026
Notes
Hydro Tasmania current fact sheet gives Butlers Gorge commissioned in 1951 and 12.2 MW; the Derwent scheme page currently lists 12.7 MW, indicating a discrepancy in published capacity figures. No plant-specific greenfield construction/investment cost was found in official owner/government sources, so capex was left blank rather than using a benchmark. Hydro Tasmania’s 2023 Tarraleah redevelopment article notes the redevelopment would decommission Butlers Gorge as part of the broader scheme, but that is a separate project and not a Butlers Gorge refurbishment cost.