Other Generators · Cape Byron Management PTY LTD · Turbine - Steam Sub Critical
Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.
13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST
Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.| Effective from | MLF |
|---|---|
| 2024-07-01 | 0.9742 |
| 2025-07-01 | 0.9518 |
| Capex total (greenfield) |
$382.17M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MW derived |
$10,056,990
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$11.00M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$289,493
Shown in table Reported / source value How this was derived Reference |
| Variable OPEX / MWh |
$14.47
Shown in table Reported / source value How this was derived Reference |
| Fuel cost / GJ |
$8.20
Shown in table Reported / source value How this was derived |
| Heat rate GJ/MWh |
13.39
Shown in table How this was derived Reference |
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 05 Jun 2026
Notes
Broadwater is an operating 38 MW biomass cogeneration plant. A secondary source states the Cape Byron Power cogeneration sites at Condong and Broadwater cost in the region of $240M when constructed in 2008; this appears to refer to the two-site package rather than Broadwater alone, so capex_total_aud is treated as an imprecise reported proxy and source confidence is medium. AEMO materials identify Broadwater as a 38 MW biomass facility; AEMO heat-rate data lists a 'New Biomass' static heat rate of 13.39 GJ/MWh, used as the best available biomass proxy. O&M values use AEMO/GHD 2025 biomass estimates as proxy assumptions.