BESS · Brendale Battery ProjectCo Pty Lt · Storage - Battery
13 Jun 2026 09:10 → 14 Jun 2026 09:10 AEST
| Capex total (greenfield) |
$210.97M
Shown in table Reported / source value |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage derived |
$514,562
Shown in table Reported / source value |
| Fixed OPEX (annual) |
$3.46M
Shown in table Reported / source value |
| Fixed OPEX / MW-yr |
$16,878
Shown in table Reported / source value |
| Variable OPEX / MWh |
$1.58
Shown in table Reported / source value |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 05 Jun 2026
Notes
Plant-specific greenfield capex was found in Akaysha Energy's project announcement as '$200M Brendale BESS'. No separate owner-disclosed full-project total beyond this figure was located. The project is a 205 MW / 410 MWh battery; the provided 204.96 MW capacity was used for per-MW calculations.