Bodangora Wind Farm (BODWF1)

Wind · Bodangora Wind Farm Pty Ltd · Wind Turbine - Onshore

Operational AEMO: In Service NSW1 Wind - Wind NEM data · 24 hours
113 MW
Registered nameplate capacity
24 hours revenue
$14.1k
Capacity factor
10.0%
Revenue / MWh
$52.19
Est. SRMC
$0.68/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
113 MW

AEMO status In Service
Project status Operational (AI)

Power Technology / Infigen Energy reports Bodangora Wind Farm commissioned in 2018–2019 and operating since 2019; Wikipedia notes fully commissioned in Dec 2018 and operating continuously since then.

Region NSW1
Coordinates -32.39600, 149.06700 (AI)

Wikipedia coordinates for Bodangora Wind Farm: 32°23′46″S 149°04′01″E.

MLF 0.9638
DUID BODWF1
Owner Bodangora Wind Farm Pty Ltd
Commissioned Feb 2019
Expected closure 2049
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM GE Renewable Energy
Turbine model 3.4-130
Equipment confidence high
Stats window
13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST

Dispatch & revenue

13 Jun 2026 00:00 → 13 Jun 2026 23:59 AEST

Energy revenue (× MLF)
$14.1k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
270.4 MWh
Available
221.0 MWh
Curtailed
MWh
Curtailment
0.0%
of available
MLF used
0.9638
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 0.9518
2025-07-01 0.9638

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
113 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.68/MWh
Capex total (greenfield)
$318.92M

Shown in table
$318.92M (2026 real AUD)

Reported / source value
$236.00M (2017 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Owner/developer announcement states the Bodangora Wind Farm total project cost is approximately A$236 million.

Reference
INFIGEN TO PROCEED TO CONSTRUCTION OF 113 MW BODANGORA WIND FARM (high confidence)
Source recorded 05 Jun 2026

Capex refurbishment
Capex / MW derived
$2,817,554

Shown in table
$2.82M (2026 real AUD)

Reported / source value
$2.08M (2017 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Derived capex per MW from the reported total project cost and registered capacity.

Reference
INFIGEN TO PROCEED TO CONSTRUCTION OF 113 MW BODANGORA WIND FARM (high confidence)
Source recorded 05 Jun 2026

Fixed OPEX (annual)
$8.41M

Shown in table
$8.41M (2026 real AUD)

Reported / source value
$6.23M (2017 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$74,324

Shown in table
$74.3k (2026 real AUD)

Reported / source value
$55.0k (2017 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No plant-specific O&M source found; used the provided fallback default.

Variable OPEX / MWh
$0.68

Shown in table
$0.68 (2026 real AUD)

Reported / source value
$0.50 (2017 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No plant-specific variable O&M source found; used the provided fallback default.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 05 Jun 2026

Notes
Greenfield project cost reported at approximately A$236 million. No refurbishment cost identified. Fixed O&M and variable O&M used as fallback defaults because no plant-specific O&M source was found in the search results.