Adelaide Desalination Plant (ADPPV1)

Solar · South Australian Water Corporation · Solar PV - Fixed

Operational AEMO: In Service SA1 Solar - Solar NEM data · 7 days
11 MW
Registered nameplate capacity
7 days revenue
$21.3k
Capacity factor
24.1%
Revenue / MWh
$47.77
Est. SRMC
$0.00/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. SA1 regional price (RRP) on right axis.

Key information
Capacity
11 MW

AEMO status In Service
Project status Operational (AI)

Renew Economy (2020) reported SA Water’s Adelaide Desalination Plant solar project as one of the proposed projects and AECOM notes the renewable-energy system for the plant was being designed as part of SA Water’s initiative; the asset is commissioned/in service by 2022-05-01 per prompt.

Region SA1
Coordinates

MLF 1.0037
DUID ADPPV1
Owner South Australian Water Corporation
Commissioned May 2022
Expected closure 2041
Closure date
Technology Solar PV - Fixed
Fuel Solar - Solar
Module OEM JA Solar
Module / inverter supplier SMA
Inverter OEM
Inverter model
Equipment confidence medium
Stats window
07 Jun 2026 00:50 → 14 Jun 2026 00:50 AEST

Dispatch & revenue

07 Jun 2026 00:50 → 14 Jun 2026 00:50 AEST

Energy revenue (× MLF)
$21.3k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
445.9 MWh
Available
450.2 MWh
Curtailed
9.3 MWh
Curtailment
2.1%
of available
MLF used
1.0037
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-01 1.0025
2025-07-01 1.0037

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Solar PV
Capacity
11 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$11.00M

Shown in table
$11.00M (2026 real AUD)

Capex refurbishment
Capex / MW derived
$1,000,000

Shown in table
$1.00M (2026 real AUD)

Fixed OPEX (annual)
$50.0k

Shown in table
$50.0k (2026 real AUD)

Fixed OPEX / MW-yr
$4,545

Shown in table
$4.5k (2026 real AUD)

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 02 Jun 2026

Notes
The fixed O&M costs are based on industry averages for solar PV systems.

Sources