Greenbank BESS (GREENB1)

BESS · CSE BESS Pty Ltd · Storage - Battery

Commissioning AEMO: In Commissioning QLD1 Other - Other NEM data · 30 days
200/400 MW
Registered nameplate capacity / storage
30 days revenue
$858.8k
Capacity factor
-1.3%
Revenue / MWh
—
Est. SRMC
$1.54/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. QLD1 regional price (RRP) on right axis.

Key information
Capacity
200 MW / 400 MWh

AEMO status In Commissioning
Project status Commissioning (AI)

Consolidated Power Projects project page (2024–2025) describes Greenbank BESS scope including commissioning; AEMO status is In Commissioning as of the provided asset data.

Region QLD1
Coordinates —

MLF 1.0035
DUID GREENB1
Owner CSE BESS Pty Ltd
Commissioned Jun 2025
Expected closure 2044
Closure date —
Technology Storage - Battery
Fuel Other - Other
Battery OEM Tesla
Battery platform / chemistry Megapack
Inverter OEM —
Inverter / PCS model —
Equipment confidence high
Stats window
26 Aug 2026 12:40 → 25 Sep 2026 12:40 AEST

Dispatch & revenue

26 Aug 2026 12:40 → 25 Sep 2026 12:40 AEST

Energy revenue (× MLF)
$858.8k
FCAS revenue (× MLF)
$2.8k
FCAS volume
45,613.1 MWh
Dispatched
-1,942.5 MWh
Available
107,930.7 MWh
Curtailed
109,886.1 MWh
Curtailment
101.8%
of available
MLF used
1.0035
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

🔋 State of charge

Stored energy at the start of each 5‑minute interval (AEMO INITIAL_ENERGY_STORAGE). Available up to the latest next‑day dispatch file.

54.5 MWh 14%
at 25 Sep 03:40 · of 400 MWh registered

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional price — dispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • State of charge — INITIAL_ENERGY_STORAGE (MWh at interval start) from UNIT_SOLUTION, published for bidirectional/storage units. Next-day data — the SOC line lags real time by up to a day.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-12-17 1.0033
2025-07-01 1.0045
2026-07-01 1.0035

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
200 MW / 400 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.54/MWh
Capex total (greenfield)
$307.38M

Shown in table
$307.38M (2026 real AUD)

Reported / source value
$300.00M (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
CS Energy states the Greenbank Battery is a $300 million project.

Reference
Greenbank Battery (high confidence)
Source recorded 08 Jun 2026

Capex refurbishment
—
Capex / MWh storage derived
$768,443

Shown in table
$768.4k (2026 real AUD)

Reported / source value
$750.0k (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Per-MWh capex was calculated from the reported project investment and stated storage capacity.

Reference
Greenbank Battery (high confidence)
Source recorded 08 Jun 2026

Fixed OPEX (annual)
$3.28M

Shown in table
$3.28M (2026 real AUD)

Reported / source value
$3.20M (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
AEMO’s BESS review indicates annual O&M for batteries is highly variable and suggests fixed O&M is typically quoted on a $/MW basis; a midpoint-style proxy was used to populate the field.

Reference
2024 Energy Technology Cost and Technical Parameter Review (medium confidence)
Source recorded 08 Jun 2026

Fixed OPEX / MW-yr
$16,393

Shown in table
$16.4k (2026 real AUD)

Reported / source value
$16.0k (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
AEMO provides indicative battery O&M values and notes they are highly variable between OEMs; a proxy value was selected for the requested output.

Reference
2024 Energy Technology Cost and Technical Parameter Review (medium confidence)
Source recorded 08 Jun 2026

Variable OPEX / MWh
$1.54

Shown in table
$1.54 (2026 real AUD)

Reported / source value
$1.50 (2025 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
No plant-specific variable O&M figure was located; batteries commonly have negligible variable O&M under long-term service arrangements.

Fuel cost / GJ
—
Heat rate GJ/MWh
—

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 08 Jun 2026

Notes
Plant-specific reported capex found in CS Energy fact sheet: $300 million investment for the 200 MW/400 MWh Greenbank Battery, commissioned in June 2025. Fixed O&M not explicitly published for this asset; used AEMO 2024 BESS indicative annual fixed O&M excluding extended warranties of $1.8m-$7.46m total annual O&M across size cases, selecting a midpoint-style proxy of ~$16,000/MW-yr for a 200 MW battery as a fallback estimate. Variable O&M is typically treated as negligible for BESS long-term service agreements; a small default of $1.50/MWh was retained from server-side fallback. No fuel or heat rate applies.

Sources