Hydro · Water NSW · Storage - Pumped hydro
14 May 2026 15:25 → 13 Jun 2026 15:25 AEST
| Capex total (greenfield) |
—
How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage |
$204,918
Shown in table Reported / source value |
| Fixed OPEX (annual) |
—
|
| Fixed OPEX / MW-yr default |
$45,000
Shown in table How this was derived |
| Variable OPEX / MWh default |
$1.20
Shown in table How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: low · Status: ai estimated · Capex basis: default · AI checked 08 Jun 2026
Notes
I could confirm the project is proposed at Glenbawn reservoirs under WaterNSW / AGL, with current design of 770 MW and 10-hour storage (7,700 MWh). I did not find a plant-specific greenfield capex announcement for Glenbawn, so no capex total was populated. WaterNSW and AGL materials describe the project as early-stage / proposed, and WaterNSW notes geotechnical investigations are expected to start in November 2025, indicating it is not yet commissioned.