14 May 2026 23:40 → 13 Jun 2026 23:40 AEST
| Capex total (greenfield) |
$120.90M
Shown in table Reported / source value How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage derived |
$604,508
Shown in table Reported / source value How this was derived Reference |
| Fixed OPEX (annual) |
$2.56M
Shown in table Reported / source value How this was derived |
| Fixed OPEX / MW-yr |
$25,615
Shown in table Reported / source value How this was derived |
| Variable OPEX / MWh |
$1.54
Shown in table Reported / source value How this was derived |
| Fuel cost / GJ |
—
|
| Heat rate GJ/MWh |
—
|
Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026
Notes
Project is a 100 MW / 200 MWh utility-scale battery. Reported Estimated Development Cost (excl GST) in NSW planning documents is AUD 118,000,000; this is used as the greenfield project cost. No plant-specific O&M, fuel, heat rate, or refurbishment cost data was found in the searched sources, so server-side defaults were used for O&M and standard battery assumptions left blank where not applicable.