Darlington Point Energy Storage System (DPNTB1)

BESS · DPESS Pty Ltd · Storage - Battery

Operational AEMO: In Service NSW1 Other - Other NEM data · 7 days
25/50 MW
Registered nameplate capacity / storage
7 days revenue
$11.3k
Capacity factor
-1.2%
Revenue / MWh
Est. SRMC
$0.00/MWh

Energy flow

Dispatch target (cleared) vs availability — 5‑minute intervals. NSW1 regional price (RRP) on right axis.

Key information
Capacity
25 MW / 50 MWh

AEMO status In Service
Project status Operational (AI)

pv magazine International, 2023; ARENA operations report indicates the battery was commissioned and operating.

Region NSW1
Coordinates -34.61100, 146.41600 (AI)

Edify Energy project page: approximately 10 km south of Darlington Point, NSW; adjacent to TransGrid Darlington Point Substation.

MLF 0.9453
DUID DPNTB1
Owner DPESS Pty Ltd
Commissioned Aug 2023
Expected closure 2051
Closure date
Technology Storage - Battery
Fuel Other - Other
Battery OEM Tesla
Battery platform / chemistry Megapack
Inverter OEM Tesla
Inverter / PCS model Megapack inverter/PCS (integrated)
Equipment confidence high
Stats window
07 Jun 2026 05:55 → 14 Jun 2026 05:55 AEST

Dispatch & revenue

07 Jun 2026 05:55 → 14 Jun 2026 05:55 AEST

Energy revenue (× MLF)
$11.3k
FCAS revenue (× MLF)
$0
FCAS volume
MWh
Dispatched
-51.1 MWh
Available
2,823.6 MWh
Curtailed
2,874.7 MWh
Curtailment
101.8%
of available
MLF used
0.9453
end of period

Revenue (× MLF)

Estimated $ per interval — energy (RRP) and FCAS (regional FCAS prices), both × MLF.

Methodology & assumptions

  • Dispatch & availability — AEMO Next Day Dispatch UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.
  • Regional pricedispatch_price RRP matched by settlement time and NEM region (from generator registry).
  • Energy revenue (× MLF) — cleared MW × (5/60 h) × RRP × MLF.
  • FCAS revenue & volume — cleared FCAS MW from DISPATCHLOAD (raise/lower 6s, 60s, 5min, reg) × (5/60 h) × regional FCAS price × MLF. Volume is total FCAS enablement MWh across services.
  • Curtailment — estimated economic curtailment when availability exceeds dispatch target: max(0, availability − cleared) × (5/60) MWh.
  • Not settlement — estimates only. AEMO settlement applies DLF, rebids, constraints, and other factors not modelled here.
MLF history (AEMO daily)
Effective fromMLF
2024-07-18 0.8774
2025-07-01 0.9453

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
25 MW / 50 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.00/MWh
Capex total (greenfield)
$37.78M

Shown in table
$37.78M (2026 real AUD)

Reported / source value
$32.34M (2022 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Confirms the project capacity and operating entity for the site.

Reference
Darlington Point Energy Storage System - Australian Renewable Energy Agency (ARENA) (high confidence)
Source recorded 07 Jun 2026

Capex refurbishment
Capex / MWh storage derived
$755,607

Shown in table
$755.6k (2026 real AUD)

Reported / source value
$646.8k (2022 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
$337.6k

Shown in table
$337.6k (2026 real AUD)

Reported / source value
$320.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX / MW-yr
$13,502

Shown in table
$13.5k (2026 real AUD)

Reported / source value
$12.8k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
AEMO/Aurecon provides a 4-hour BESS fixed O&M benchmark; this was the closest available storage O&M proxy.

Reference
2024 Energy Technology Cost and Parameters Review (medium confidence)
Source recorded 07 Jun 2026

Variable OPEX / MWh
$0.00

Shown in table
$0.00 (2026 real AUD)

Reported / source value
$0.00 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
The benchmark indicates no separate variable O&M is typically assumed for BESS long-term service agreements.

Reference
2024 Energy Technology Cost and Parameters Review (medium confidence)
Source recorded 07 Jun 2026

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: high · Status: ai estimated · Capex basis: reported · AI checked 07 Jun 2026

Notes
Plant-specific total project cost reported by ARENA for the 25 MW / 50 MWh Darlington Point Energy Storage System. The ARENA project page lists $32.34m total project cost, with Edify Energy operating as DPESS DevCo. For O&M, AEMO/Aurecon 2024 benchmark for a co-located 4-hour BESS was used as the closest available template; there was no site-specific O&M figure located. BESS benchmark values are for a hypothetical 200 MW plant, so the per-MW O&M assumption is a scaled benchmark, not a reported project value. Efficiency and life assumptions are from AEMO/Aurecon BESS technical parameters.

Sources