Camperdown BESS - Quintas

BESS · Camperdown BESS Pty Ltd · Storage - Battery

Development AEMO: Publicly Announced Other - Other NEM data · 24 hours
75/150 MW
Researched capacity / storage
Est. SRMC
$1.50/MWh
Key information
Capacity (AI)
75 MW / 150 MWh

User-provided AEMO spreadsheet/project brief: 75 MW / 150 MWh.

AEMO status Publicly Announced
Project status Development (AI)

Owner/planning information was not available in the provided search results; project is still publicly announced and not yet commissioned per user-provided project data.

Coordinates —

DUID —
Owner Camperdown BESS Pty Ltd
Commissioned Dec 2026
Expected closure —
Closure date —
Technology Storage - Battery
Fuel Other - Other
Battery OEM —
Battery platform / chemistry —
Inverter OEM —
Inverter / PCS model —
Equipment confidence low
Stats window
24 Sep 2026 00:00 → 24 Sep 2026 23:59 AEST

Dispatch & revenue

24 Sep 2026 00:00 → 24 Sep 2026 23:59 AEST

No DUID specified. Open this page from the stats list or a generator profile.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Battery (BESS)
Capacity
75 MW / 150 MWh
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$1.50/MWh
Capex total (greenfield)
$55.38M

Shown in table
$55.38M (2026 real AUD)

Reported / source value
$52.50M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex refurbishment
—
Capex / MWh storage derived
$369,198

Shown in table
$369.2k (2026 real AUD)

Reported / source value
$350.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Fixed OPEX (annual)
—
Fixed OPEX / MW-yr default
$25,000

Shown in table
$25.0k (2026 real AUD)

Variable OPEX / MWh default
$1.50

Shown in table
$1.50 (2026 real AUD)

Fuel cost / GJ
—
Heat rate GJ/MWh
—

Confidence: low · Status: ai estimated · Capex basis: default · AI checked 05 Jun 2026

Notes
No plant-specific greenfield capex announcement was found in the searches provided or additional web searches. Public pages confirm the project and applicant/owner, but do not disclose a total project investment. The available ARES project page describes a 60 MW / 240 MWh Camperdown BESS, which conflicts with the user-provided 75 MW / 150 MWh site data and therefore was not used for financial inference.

Sources