Boco Rock Wind Farm (BOCOROC2)

Wind · South Pacific Power Pty Ltd · Wind Turbine - Onshore

Development AEMO: Publicly Announced NSW1 Wind - Wind NEM data · 24 hours
80 MW
Registered nameplate capacity
Est. SRMC
$0.53/MWh
Key information
Capacity
80 MW
AEMO status Publicly Announced
Project status Development (AI)

Region NSW1
DUID BOCOROC2
Owner South Pacific Power Pty Ltd
Commissioned
Expected closure 2025-07-02
Closure date
Technology Wind Turbine - Onshore
Fuel Wind - Wind
Turbine OEM
Turbine model
Stats window
03 Jun 2026 17:30 → 04 Jun 2026 17:30 AEST

Dispatch & revenue

03 Jun 2026 17:30 → 04 Jun 2026 17:30 AEST

No dispatch data for DUID BOCOROC2 in this period.

Financial overview

2026 real AUD. Monetary values are CPI-adjusted to 2026 real Australian dollars. Greenfield capex uses AEMO benchmarks when plant-specific cost is unknown.
Type
Wind (onshore)
Capacity
80 MW
Revenue (× MLF) (stats)
See dispatch stats link above
Est. SRMC
$0.53/MWh
Capex total (greenfield)
$184.49M

Shown in table
$184.49M (2026 real AUD)

Reported / source value
$174.90M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex refurbishment
Capex / MW
$2,320,675

Shown in table
$2.32M (2026 real AUD)

Reported / source value
$2.20M (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

Capex / MWh storage
Fixed OPEX (annual)
$4.61M

Shown in table
$4.61M (2026 real AUD)

Reported / source value
$4.38M (2024 nominal)
Table total may differ if recalculated from $/MW × registered capacity after CPI adjustment.

Fixed OPEX / MW-yr
$58,017

Shown in table
$58.0k (2026 real AUD)

Reported / source value
$55.0k (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Internal server-side default retained because AEMO fixed O&M values for onshore wind could not be extracted into the required CAPEX/O&M fields for this DUID within the performed document retrieval.

Variable OPEX / MWh
$0.53

Shown in table
$0.53 (2026 real AUD)

Reported / source value
$0.50 (2024 nominal)
Adjusted to 2026 real AUD using Australian CPI (All Groups).

How this was derived
Internal server-side default retained due to missing verified AEMO variable O&M for wind_onshore in the extracted sources for this run.

Fuel cost / GJ
Heat rate GJ/MWh

Confidence: low · Status: ai estimated · Capex basis: default · AI checked 04 Jun 2026

Notes
Web search did not reliably return plant-specific commissioning date or greenfield CAPEX for BOCOROC2, nor any brownfield upgrade spend. O&M defaults were retained due to missing AEMO wind-onshore retirement/O&M estimate review alignment with the required cost base-year/currency basis for this specific DUID; please re-run with AEMO GenCost/ETC ‘onshore wind’ CAPEX and O&M for the latest published review tables.

Sources

  • asset_life_years (low)
  • fixed_opex_per_mw_year_aud (low)
  • variable_opex_per_mwh_aud (low)