BESS · Ausnet Transmission Group Pty Ltd · Storage - Battery
Dispatch target (cleared) vs availability — 5‑minute intervals. VIC1 regional price (RRP) on right axis.
03 Jun 2026 20:55 → 04 Jun 2026 20:55 AEST
Estimated $ per interval using regional RRP and MLF effective on each day.
UNIT_SOLUTION (5‑minute intervals). Intervention intervals excluded.dispatch_price RRP matched by settlement time and NEM region (from generator registry).| Effective from | MLF |
|---|---|
| 2024-07-18 | 0.9605 |
| 2025-07-01 | 0.9766 |
| Capex total (greenfield) |
$42.66M
Shown in table How this was derived Reference |
|---|---|
| Capex refurbishment |
—
|
| Capex / MWh storage derived |
$1,422,000
Shown in table How this was derived Reference |
| Fixed OPEX (annual) |
$270.0k
Shown in table How this was derived Reference |
| Fixed OPEX / MW-yr |
$9,000
Shown in table How this was derived Reference |
| Variable OPEX / MWh |
$0.00
Shown in table How this was derived Reference |
| Fuel cost / GJ |
—
How this was derived Reference |
| Heat rate GJ/MWh |
—
How this was derived Reference |
Confidence: medium · Status: ai estimated · Capex basis: reported · AI checked 04 Jun 2026
Notes
Capex: ARENA project page reports total project cost of AUD 42.66m; a 2019 knowledge-sharing report also states project value of AUD 33.2m, likely a narrower D&C/substantial completion value. The financial profile uses ARENA total project cost as the broadest reported nominal project cost and preserves 2018 commissioning/commercial operation year. O&M: no Ballarat-specific dollar O&M amount was found; fixed O&M is estimated/defaulted using Aurecon/AEMO 2024 1-hour large-scale BESS assumptions: AUD 5,400/MW-year fixed O&M plus AUD 3,600/MW-year extended warranty, scaled to 30 MW = AUD 270,000/year. Variable O&M is set to 0 because Aurecon reports BESS long-term service agreements are not typically split into fixed/variable and variable O&M is shown as dash/included in fixed service costs. Efficiency is Ballarat-specific round-trip efficiency, averaged/rounded from contract year 1 and 2 operating parameters of 87.17% and 86.80%. Emissions intensity is direct operational emissions only; it excludes upstream emissions associated with charging electricity. Asset life uses a default modern lithium-ion BESS technical/economic life of 20 years; Ballarat-specific documentation confirms a 15-year Fluence service agreement but no explicit closure date. Major refurbishment/operational note: a battery replacement program was completed in contract year 2 after SoC restrictions affected availability; the report expected availability without the SoC restriction to reach approximately 99%.